The Overall Acceptance of Mali New Sukala EPC Project (Industrial Section) Was Accomplished Edit Date:2016/01/07



       On 19th Dec 2015, Sinolight Corporation organized the acceptance meeting of Mali New Sukala 6000 TCD Sugar Factory Project participated with industrial experts and Group staff in Mali New Sukala Company. The Acceptance Group finally approved the acceptance after reviewing the report by constructional company and relevant documents, construction site inspection, meeting enquiry and examination.
       This result marked the final accomplishment of this project with 5-year effort of relevant project parties. Sincere gratefulness would like to be sent to all constructional parties including constructional companies, supporting companies and all project staff.